發(fā)包方(簡稱甲方)
Party?A:?
?
承包方(簡稱乙方):
根據(jù)<中華人民共和國合同法><中華人民共和國消費者權(quán)益保護法><中華人民共和國價格法><上海市合同格式條款監(jiān)督條例>,<上海市建筑市場管理條例>,以及其他有關(guān)法律法規(guī)規(guī)定的原則,結(jié)合本工程的具體情況,甲、乙雙方在平等、自愿、協(xié)商一致的基礎(chǔ)上達成如下協(xié)議,共同遵守
?
According?to:?“PRC?Contract?Law”,?“Law?on?the?Protection?of?Consumer?Interests”,?“PRC?Price?Law”,?“Shanghai?Supervision?of?Contract?Terms”,?“Shanghai?Construction?Market?Management?Regulations”,?as?well?as?other?laws?and?regulations?relevant?to?the?specific?circumstances?of?this?project,?parties?A?and?B?have?hereby?equally?and?voluntarily?entered?into?the?following?agreement?executed?on?the?basis?of?mutual?respect.
?
一、概況
OVERVIEW
??? 1.??甲方裝飾物業(yè)系合法物業(yè)
Party?A?is?the?owner?of?the?property.
2.??乙方為本市經(jīng)工商行政管理機關(guān)核準(zhǔn)登記,并可從事裝潢裝修的企業(yè)
Party?B?is?approved?and?registered?with?the?city?industrial?and?commercial?administrative?organs?as?an
enterprise?engaged?in?renovation?and?decoration.?
3.??裝飾施工地點
Construction?site:?
4.??建筑結(jié)構(gòu):?????????????????建筑面積???????平方米,施工面積????????平方米。
Construction?area:?total?area?(including?stairwells?and?other?common?areas):?????m2,?private?living?area:???m2.
5.??裝飾施工內(nèi)容:住宅裝飾,詳見附件一<工程估價單>
Structure:?residential.
6.??承包方式:詳見附件一<工程估價單>
Contractor?engagement?method:?See?annex?–?(quotation).
7.??總價款:????????????.00元,大寫(人民幣):????????????????????????????元整。
Total?price:??????????.00RMB;?in?words:?????????????????????元整.?Any?changes?in?this?price?must?be?agreed?by?both?parties?in?writing.
8.??工期:自?????年??月??日開工,至??????年???月???日前竣工,工時總計???天,不含國家法定節(jié)假日,乙方委派現(xiàn)場施工監(jiān)理為????????????先生,聯(lián)系方式:?
Period:?Start:?????(year)???(month)???(day);?Completion?before:????(year)????(month)??(day);?Total?days?(excluding?national?holidays):???days.?Party?B's?on?site?construction?supervisor?will?be:??
二、關(guān)于工程付款及結(jié)算的約定???
TERMS?OF?PAYMENT???
1.??工程款的付款方式如下
The?payment?schedule?shall?be?as?follows:???
?
? | 付???款???時???間 Timing?of?Payments | 付??款??時??間 Date?(yyyy.mm.dd) | Amount?(RMB) |
合同簽訂后60% After?the?contract?is?signed. | ? | ? | ? |
油漆工進場前30% When?half?of?the?project?period?time?has?elapsed. | ? | ? | ? |
家具、燈具進場前5% Furniture?of?lamps?and?lanterns,?before?the?approach | ? | ? | ? |
驗收合格后,五天內(nèi)5% Upon?Acceptance?of? the?completion?of?the?project. | ? | ? | ? |
增加工程項目100% Project?changes. | 簽訂工程項目變更單100% Date?of?signing?for?the?project?change. | ? | ? |
空調(diào)工程項目100% Air?conditioning?project | ? | ? | ? |
家具工程項目100% Furniture?engineering | ? | ? | ? |
????
三、關(guān)于材料供應(yīng)的約定
AGREEMENT?ON?THE?SUPPLY?OF?MATERIALS
1.??乙方提供的材料:乙方供應(yīng)的材料、設(shè)備,如不符合設(shè)計、施工要求,應(yīng)禁止使用。如已使用,對工程造成的損失由乙方負(fù)責(zé)。如甲方要另增加材料由甲方供應(yīng),并應(yīng)符合下列規(guī)定:
????????Material?provided?by?Party?B:?Any?materials?or?equipment?supplied?by?Party?B?which?do?not?meet?the?design?and?construction?requirements?are?prohibited.?Any?extra?materials?requested?by?Party?A?which?were?not?in?the?original?design?must?be?paid?for?by?Party?A.
????2.??甲方提供的材料:另擬補充附件<甲方提供材料、設(shè)備表>
甲方負(fù)責(zé)采購供應(yīng)的材料、設(shè)備,應(yīng)符合設(shè)計施工要求的合格產(chǎn)品,并應(yīng)按時供應(yīng)到現(xiàn)場。乙方發(fā)現(xiàn)甲方提供的材料、設(shè)備有質(zhì)量問題或規(guī)格差異,應(yīng)及時向甲方提出,甲方仍要求使用的,由此造成工程損失,責(zé)任由甲方承擔(dān)。甲方供應(yīng)的材料按時抵達現(xiàn)場后,由乙方負(fù)責(zé)保管
????Material?provided?by?Party?A:?(see?the?annex:?“Table?of?Materials?to?be?provided?by?the?Owner”).??If?Party?A?acquires?materials?for?the?project,?it?should?first?check?with?Party?B?that?the?materials?match?to?the?design?requirements,?and?once?the?materials?are?in?the?care?of?Party?B,?then?Party?B?is?responsible?for?the?materials.?If?Party?A?requires?some?materials?which?do?not?fit?to?the?design?then?it?shall?be?the?responsibility?of?Party?A?to?pay?any?additional?costs?incurred?by?Party?B.????
四、關(guān)于工程質(zhì)量及驗收的約定
FULFILMENT?OF?THIS?AGREEMENT
?????1.?本工程應(yīng)符合<建筑裝飾工程技術(shù)規(guī)程>和市建設(shè)行政主管部門制定的其它地方標(biāo)準(zhǔn)\質(zhì)量評定驗收標(biāo)準(zhǔn)
The?execution?of?this?project?must?be?consistent?with?the?“Architectural?and?Engineering?Rules”?of?the?city?administrative?departments?responsible?for?the?development?of?buildings?and?local?standards?and?quality?evaluation?acceptance?criteria.?
2.?本工程由乙方進行設(shè)計,提供施工圖紙一式兩份,雙方簽字確認(rèn)
Party?B?must?provide?a?duplicate?copy?of?the?construction?designs?and?drawings,?and?both?copies?should?be?signed?by?both?parties.
?3.??甲方提供的材料、設(shè)備質(zhì)量不合格而影響工程質(zhì)量,其返工費用由甲方承擔(dān),工期相應(yīng)順延
If?materials?provided?by?Party?A?for?the?construction?do?not?meet?the?necessary?requirements,?Party?A?shall?bear?responsibility?for?any?resulting?delays?in?the?completion?in?the??project.?
?4.??由于乙方原因造成質(zhì)量事故,其返工費用由乙方承擔(dān)
If?the?quality?of?Party?B's?work?results?in?any?accidents,?the?liability?for?such?accidents?shall?be?the?responsibility?of?Party?B.
5.??在施工過程中,甲方提出設(shè)計修改意見及增減工程項目,須提前與乙方聯(lián)系,在雙方簽訂<工程項目變更單>后,方能進行該項目的施工、因此影響工程竣工日期的,責(zé)任由甲方承擔(dān)。凡甲方私自與施工人員商定更改施工內(nèi)容、增加施工項目所引起的一切后果,甲方自負(fù),給乙方造成損失的,甲方應(yīng)予賠償
If,?during?the?construction,?Party?A?wishes?to?propose?a?change?to?the?design,?he?should?sign?a?“Change?of?Project”?with?Party?B?and?must?assume?responsibility?for?resulting?delays?or?increase?in?costs.?If?Party?A?secretly?attempts?to?change?to?design?directly?with?the?construction?personnel?and?this?action?causes?loss?to?Party?B,?then?Party?A?must?compensate?Party?B?for?this?loss.?
6.??工程驗收:乙方負(fù)責(zé)理隱蔽工程和中間工程的檢查與驗收手續(xù)。由乙方組織專門人員進行驗收。一切理隱蔽工程和中間工程的質(zhì)量由乙方負(fù)責(zé)
The?standard?of?work.?It?is?the?responsibility?of?Party?B?to?make?sure?that?all?construction?works?are?carried?out?to?the?requirements?of?the?design?and?to?make?sure?that?all?internal?walls?and?hidden?construction?parts?are?to?the?required?standard.
?7.??工程竣工:乙方完工后即應(yīng)通知甲方驗收,甲方應(yīng)在竣工當(dāng)日組織驗收,并辦理驗收移交手續(xù),雙方簽<工程質(zhì)量驗收單>。如果甲方在規(guī)定時間內(nèi)不能組織驗收,須及時通知乙方,另定驗收日期。如通過竣工驗??收,甲方應(yīng)承認(rèn)原竣工日期,并承擔(dān)因此造成的乙方的看管費用和其他相關(guān)費用
Project?completion.?Party?B?must?notify?Party?A?when?the?project?is?complete?and?ready?for?inspection?by?Party?A.?After?inspection?both?parties?must?sign?an?“Engineering?Quality?Acceptance”?document.?If?Party?A?is?not?available?to?inspect?the?construction?site?on?the?completion?date,?he?must?notify?Party?B?of?the?soonest?available?date.?Where?Party?A?is?not?available?on?the?completion?date?to?retake?custody?of?the?location,?he?must?pay?any?extra?costs?incurred?by?Party?B.?
?8.??工程保修期一年。工程竣工驗收后甲、乙雙方簽署<工程保修單>,憑保修單實行保修,保修期一年,從竣工驗收簽章之日起算
One?year?warranty.?After?completion?of?the?work?and?signing?of?the?“Single?Warranty”,?there?shall?be?a?one?year?warranty?on?the?construction.